Verdad Resources is proposing a 22 well horizontal drilling project called the Century Pad, located south of Weld County Road 74 (Harmony Road), extending from South County Road 5 past County Road 15 near Windsor, Colorado. The proposed 18-acre surface pad is in unincorporated Weld County, but the proposed Oil and Gas Development Plan (OGDP) intends to extract minerals from both Weld and Larimer Counties in a 3,000-acre drilling and spacing unit (DSU), shown in a dashed red outline in the map above.

There are 10 existing residential building units (RBUs) within 2,000 ft of the proposed pad, which triggers additional requirements for Weld County; Verdad must submit additional noise, dust, and odor mitigation plans, and must conduct a baseline ambient noise survey.

View a full version of the proposed Century OGDP map, or order a 24″ x 36″ printed map.

The Process

ogdp phases century 01

As of August 5, 2026, Weld County has deemed the Century application complete; a hearing with the Weld County Commissioners is currently scheduled for October 1, 2026. If the drilling project is approved by the Weld County Commissioners, Verdad will file with the Colorado Energy and Carbon Management Commission (ECMC) for a state-level permit, which typically takes 12 to 24 months. Verdad currently plans to begin construction at the Century pad in February 2027, which seems unlikely given the normal ECMC approval process timelines.

faq

Contacts

For questions related to the OGDP Application or the Century Location, you may contact the following
individuals at Verdad:

Jeff Berghorn – Vice President of Land
1125 17th St.
Suite 600
Denver, CO 80202
720-845-6912
jberghorn@verdadresources.com

Heather Mitchell – Dir. of Regulatory Affairs
1125 17th St.
Suite 600
Denver, CO 80202
720-845-6917
hmitchell@verdadresources.com

Weld County is the Relevant Local Government. Inquiries to the County may be directed to:

Tyler Seno – Regulatory Analyst II
1402 N. 17th Ave.
Greeley, CO 80631
970-400-5172
tseno@weld.gov

If you’re not getting straight answers from any of the above, our team has been following this project closely and is happy to help. Feel free to contact us directly.

More Information

We’ve assembled the documents below from various sources, including the Weld County Oil and Gas Portal. Check back often, as they will definitely change in the next weeks and months as the application moves through the Weld County and ECMC permitting process.

Open House Packet
The public-facing mailer for the November 3, 2025 open house held at the Windsor Community Center. Last updated Oct 15, 2025.
Ambient Sound Level Survey
Behrens and Associates’ baseline noise measurements, taken at three locations around the site before construction began. Last updated Oct 30, 2025.
Noise Mitigation and Monitoring Plan
Verdad’s plan for keeping drilling, completions, and production noise within county limits, including sound wall designs. Last updated Jul 31, 2026.
Required Information & Site Selection Narrative
Verdad’s core project narrative, covering well count, acreage, schedule, and why the company chose this site over seven alternatives. Last updated Aug 5, 2026.
Facility Drawings & Photos
Site maps and equipment diagrams showing the pad layout, nearest homes, and production equipment. Last updated Aug 6, 2026.
Light Mitigation Plan
Uintah Engineering’s plan for controlling nighttime lighting during construction, drilling, and production near neighbors and wildlife. Last updated Aug 7, 2026.
Odor Mitigation Plan
Verdad’s plan for limiting odors reaching nearby homes, including equipment choices and a 24/7 complaint contact. Last updated May 14, 2026.
Dust Mitigation Plan
Verdad’s plan for controlling dust from the access road and site during construction and drilling. Last updated May 13, 2026.
Traffic & Access Permit Application
Verdad’s application to build the site’s approach road onto Weld County Road 15, including expected truck traffic by phase. Last updated Apr 13, 2026.
Emergency Action Plan & Tactical Response Plan
Verdad’s plan for responding to spills, fires, or other emergencies at the site, including who to call for help. Last updated Apr 8, 2026.
Best Management Practices
Verdad’s summary of the safety and environmental practices it commits to on site, from sound walls to spill response. Last updated Aug 5, 2026.
Drainage & Erosion Control Report
609 Consulting’s plan for managing stormwater runoff and preventing erosion at the site during and after construction. Last updated Nov 21, 2025.
Waste Management Plan
Verdad’s plan for hauling and disposing of drilling waste, including which facilities will receive it. Last updated May 13, 2026.
Notification Zone Drawing
A map showing the required 2,000-foot notification zone around the site and the homes within it. Last updated Oct 16, 2025.

Disclaimer

This web application was compiled from documents in Verdad Resources’ Weld County 1041 WOGLA application, including county and state agency correspondence, the applicant’s Site Selection and Alternatives analysis, and other publicly available information and data. This page is for community information purposes; it is not a substitute for reviewing the official case file with the Weld County Oil & Gas Energy Department.

Call To Action

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.